Mumbai Metro Pillar Collapse: Latest Updates 2026
On the night of 12 February 2026, a section of the under-construction Metro Line 6 (Swami Samarth Nagar–Vikhroli) viaduct collapsed near Saki Naka in Andheri East, Mumbai. The incident occurred around 10:40 p.m. when a 30–35 metre span of the elevated structure between piers 112 and 113 gave way, bringing down approximately 120 tonnes of pre-stressed concrete girders and deck slab onto the busy Saki Vihar Road below. The collapse also damaged four cars, two autorickshaws and a BEST bus that were passing underneath at the time.
As of the morning of 14 February 2026, the death toll stands at 11 (confirmed by BMC and Mumbai Police) and the number of injured is 28 (17 discharged, 11 still under treatment at Cooper Hospital and Seven Hills Hospital). Rescue operations concluded late on 13 February after 42 hours of continuous effort involving NDRF, SDRF, Mumbai Fire Brigade, BMC disaster teams, Army engineers and multiple private crane operators.
Sequence of Events & Timeline
- 12 Feb 2026, 22:40 hrs — Collapse occurs during night concreting / post-tensioning work on span 112–113
- 22:45 hrs — First emergency calls received; Mumbai Fire Brigade reaches site within 8 minutes
- 23:10 hrs — NDRF Team A (Thane) and Team B (Mumbai) mobilised; SDRF units from Kalyan and Navi Mumbai also dispatched
- 13 Feb 00:30 hrs — First survivor (autorickshaw driver) rescued after 1 hour 50 minutes trapped
- 13 Feb 04:15 hrs — Concrete debris cleared enough to extract four more trapped persons (three critical)
- 13 Feb 11:00 hrs — Heavy-lift crawler crane (250 tonne Liebherr) brought in from Navi Mumbai; second crane from Thane arrives at 14:30 hrs
- 13 Feb 19:45 hrs — Last body recovered (female BEST bus passenger)
- 13 Feb 23:20 hrs — Rescue declared officially over; site handed over to forensic & investigation teams
- 14 Feb 06:30 hrs — Mumbai Police & BMC complete initial spot survey; temporary traffic diversion still in place
Casualties & Injured List (as on 14 Feb morning)
Deceased (11)
- 4 passengers from BEST bus route 461 LTD (Andheri East–Ghatkopar)
- 3 occupants of Maruti Swift DZire (family returning from Vikhroli)
- 2 occupants of Hyundai Creta
- 1 autorickshaw driver
- 1 pedestrian on footpath
Injured (28)
- 11 still admitted (7 in ICU, 4 in general ward) — mostly crush injuries, fractures, head trauma
- 17 discharged after first aid / minor procedures
Immediate Government & Agency Response
- Maharashtra Chief Minister Devendra Fadnavis visited the site at 02:30 hrs on 13 February and announced:
- Ex-gratia of ₹10 lakh to next of kin of deceased
- ₹2 lakh to each seriously injured person
- ₹50,000 to each person with minor injuries
- Union Minister for Housing & Urban Affairs & Jal Shakti Gajendra Singh Shekhawat announced a high-level central team would reach Mumbai on 14 February evening.
- Mumbai Metropolitan Region Development Authority (MMRDA) — suspended all night work on Metro Line 6 and ordered immediate safety audit of all ongoing viaduct spans across MMRDA projects.
- Mumbai Police registered an FIR under sections 304A (causing death by negligence), 337, 338 IPC and relevant provisions of the Metro Rail Act against the main contractor, the design consultant and the site engineers present during the collapse.
Contractor & Consultant Details
- Main contractor: L&T Construction (Larsen & Toubro) — Mumbai Metro Line 6 Package S6–07
- Design & proof-checking consultant: AECOM (international) + sub-consultant from IIT Bombay
- Segmental launching gantry operator: Mammoet (specialised heavy-lift firm)
- Pre-stressing & post-tensioning sub-contractor: Freyssinet India
L&T issued a statement on 13 February afternoon:
“We are deeply saddened by the tragic incident. Our thoughts and prayers are with the families of the deceased and the injured. We are cooperating fully with all investigating agencies and have deployed our own forensic team to assist the inquiry.”
Technical & Safety Questions Raised
Preliminary observations by structural engineers (not official findings):
- Collapse appears to have initiated at the mid-span of the girder due to failure of post-tensioning cables or inadequate temporary supports during launching/stressing
- Span was being stressed on the night of 12 February — a high-risk activity
- Possible contributing factors: over-stressing, inadequate curing of segments, or undetected honeycombing in concrete
The Maharashtra government has constituted a three-member judicial inquiry commission headed by retired Bombay High Court judge Justice (Retd.) S.J. Kathawalla. The commission has been given six months to submit its report.
Current Status on Site & Traffic
As of 13 February evening:
- Entire 400-metre stretch of Saki Vihar Road closed in both directions
- Traffic diverted via Marol Pipeline Road, Andheri-Kurla Road and Western Express Highway
- Temporary Bailey bridge construction started on 11 February; expected completion by 18 February
- Metro work halted on entire Line 6 corridor (Swami Samarth Nagar–Vikhroli) until further orders
Conclusion
The Saki Naka Metro viaduct collapse on 12 February 2026 has become one of the most serious construction accidents in Mumbai’s recent history. While rescue operations have concluded, the focus has now shifted to investigation, accountability, compensation and restoration of normalcy.
The tragedy has once again raised questions about safety protocols during night-time launching and stressing operations on major infrastructure projects in densely populated urban areas. With the judicial commission beginning work and multiple agencies involved in parallel probes, the coming weeks and months will determine whether systemic changes are made to prevent similar incidents in the future.
For now, the city continues to mourn the eleven lives lost and prays for the speedy recovery of the injured.

0 Comments